Community Alerts

Posted on: November 14, 2017

Road Closure - Sewanee Road (Metro)

1143 Sewanee Rd_Road Closure Map

Anticipated Construction Duration: 18 weeks
Anticipated Schedule for Construction: Begin Construction – November 13, 2017
Project Status: Gas line relocation complete, NES pole has been installed, relocation of Comcast services to new pole is complete, and right of entry agreements have been acquired.

Construction Challenges:
 Requires detour
 Requires storm infrastructure
 Repair driveway at 1144 Sewanee Road as necessary due to trench limits
 Proximity of existing stone columns
 Proximity of antique wrought iron fence
 Requires ROW

Additional Info...
Facebook Twitter Google Plus Email